Title: Resolution 22-R70, A Resolution Approving the Preliminary and Final Plat with Construction Plans for Telaro at Southern Grove Phases 2 and 3. (P21-244)
Attachments: 1. Resolution, 2. Preliminary and Final Plat, 3. Landscape Plans, 4. Construction Plans, 5. Staff Report, 6. Public Works Memo, 7. Staff Presentation

Placement: Resolutions                     

Action Requested: Motion / Vote                     

title

Resolution 22-R70, A Resolution Approving the Preliminary and Final Plat with Construction Plans for Telaro at Southern Grove Phases 2 and 3. (P21-244)  

body

Submitted By: Laura H. Dodd, AICP

 

Strategic Plan Link: The City’s Mission to plan for smart and balanced growth.

 

Executive Summary (General Business): An application for preliminary and final subdivision plat and construction plan approval for Telaro at Southern Grove Phase 2-3.  The project consists of 257 single-family lots, a conservation tract, water management tracts, private road right of way, and other associated infrastructure improvements upon 87.8 acres. 

 

Presentation Information: Staff may provide a brief presentation.

 

Staff Recommendation: Move that the Council approve the request with conditions.

 

Alternate Recommendations:

1.                     Move that the Council amend the recommendation and approve the request with conditions.

2.                     Move that the Council not approve and provide staff direction.

 

Background: The preliminary and final plat was approved by SPRC on February 23, 2022.

 

Issues/Analysis: See staff report.

                     

Financial Information: n/a

 

Special Consideration: Staff is recommending approval with the guidance of imposing one of the two transportation improvement conditions expressed in the traffic analysis, or as Council determines acceptable based upon their deliberations. If Council deliberations provide for a condition of approval, an updated resolution outlining these provisions shall be drafted for immediate execution.  

 

Location of Project: South of Discovery Way, East of SW Community Blvd., and West of SW Village Park Way

 

Attachments: 1. Resolution 2. Preliminary and Final Plat 3. Landscape Plans 4. Construction Plans 5. Public Works Memo 6. Staff Report 7. Staff Presentation

 

NOTE: All of the listed items in the “Attachment” section above are in the custody of the City Clerk. Any item(s) not provided in City Council packets are available upon request from the City Clerk.

 

Internal Reference Number: 8429

 

Legal Sufficiency Review: 

Reviewed by Elizabeth L. Hertz, Senior Deputy City Attorney. Approved as to Legal form and sufficiency by James D. Stokes, City Attorney.