City of Port St. Lucie header
File #: 2023-409    Version: 1 Name:
Type: Consent Status: Passed
File created: 4/24/2023 In control: City Council
On agenda: 5/8/2023 Final action: 5/8/2023
Title: Ratify Amendments #1, #3 and #4 and Approve Amendment #5 to Contract #20200077 for the Port St. Lucie Blvd. Segment #3 Roadway Improvement Project from Darwin Blvd. to Gatlin Blvd.
Attachments: 1. Location Map, 2. 20200077-06 Amendment #5 jmz, 3. 20200077-05-A4, 4. 20200077-05-A3, 5. 20200077-05-A2, 6. 20200077-05-A1, 7. 20200077-05

Placement: Consent Agenda                     

Action Requested: Motion / Vote                     

title

Ratify Amendments #1, #3 and #4 and Approve Amendment #5 to Contract #20200077 for the Port St. Lucie Blvd. Segment #3 Roadway Improvement Project from Darwin Blvd. to Gatlin Blvd.

body

 Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

 

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

 

Summary Brief (Agreements/Contracts only)

1.                     Prepared by: Robyn Holder, CPPB (PMD).

2.                     Parties: City of Port St. Lucie and Zahlene Enterprises, Inc.

3.                     Purpose: To bridge the gap between the FDOT project and the City’s project for a consistent roadway section through the corridor.

4.                     New/Renewal/Modified: Modified.

5.                     Duration: An additional 3 calendar days are required for a new end date of 6/26/2023.

6.                     Benefits to Port St. Lucie: The work will provide additional intersection capacity, accessible multi-use pathways, pedestrian lighting, and underground drainage.

7.                     Cost to Port St. Lucie (Annual and Potential): The total amount of the Amendments exceeds the threshold and requires Council approval in the amount of $43,836.27. The new Contract amount is $8,052,174.45.

 

Presentation Information: N/A.

 

Staff Recommendation: Move that the Council approve Amendment No. 5 to Contract No. 20200077 for the Port St. Lucie Blvd. Segment No. 3 Roadway Improvement Project with Zahlene Enterprises, Inc., and ratify prior Amendments Nos. 1, 3 and 4.

 

Alternate Recommendations:

1.                     Move that the Council amend the recommendation, ratifying Amendments Nos. 1, 3 and 4, and not approving Amendment No. 5 to Contract No. 20200077, providing staff with direction

2.                     Move that the Council not ratify Amendments Nos. 1, 3 and 4 and not approve Amendment No. 5 to Contract No. 20200077 and provide staff with direction.

 

Background: The Amendments include the following:

                     Amendment No. 1 - Additional funds needed to change out the proposed pipe from PVC to Ductile Iron. When using Ductile Iron pipe, it is required to use a polyethylene wrap. This wrap is labor intensive therefore the additional funds will be used for labor to wrap the pipe. Total cost is $8,790.25. No additional calendar days are required. (Not previously approved by Council).

 

                     Amendment No. 2 - Additional funds needed to upgrade the Mast Arm to the 12-sided Mast Arms to match all of the existing mast arms in this corridor. Total cost is $17,904.30. No additional days are required. (City Council approved on June 13, 2022, Item 7.e. - Legistar ID 2022-481)

 

                     Amendment No. 3 - Added 94 calendar days to the contract to allow for delays in procuring materials, inclement weather days and holidays. Total cost is $0.00. (Not previously approved by Council).

 

                     Amendment No. 4 - Incorporate plan revisions to the contract. Plan Revision #1 resolves sidewalk conflict with existing utility pole at the SW corner of Darwin Blvd. and Port St. Lucie Blvd. Plan Revision #2 allows for the installation of an alternative adaptive signal control system other than the Rhythm Manufacturing system specified in the original plans. (Not previously approved by Council).

 

                     Amendment No. 5 - Plan Revision to allow for the construction of alternative slope protection and address locations as noted. Total cost is $19,141.72 and 3 additional calendar days. (Not previously approved by Council).

 

Issues/Analysis: Staff has reviewed the proposed changes described herein and finds them to be fair and reasonable.

                     

Financial Information: Funds are appropriated in the Road & Bridge CIP Fund / Traffic / Improvements O/T Building / SW Port St. Lucie Blvd. Reconstruction (#304-4121-563000-Y1717).

 

Special Consideration: N/A.

 

Location of Project: Port St. Lucie Blvd from Gatlin Blvd. to Darwin Blvd.

 

Attachments:

1.                     Location Map.

2.                     Amendment No. 5 - signed.

3.                     Amendment No. 4.

4.                     Amendment No. 3.

5.                     Amendment No. 2.

6.                     Amendment No. 1.

7.                     Original Contract.

 

NOTE: All of the listed items in the “Attachment” section above are in the custody of the City Clerk. Any item(s) not provided in City Council packets are available upon request from the City Clerk.

 

Internal Reference Number: 10058

 

Legal Sufficiency Review: 

Reviewed by Ella M. Gilbert, Senior Deputy City Attorney. Approved as to Legal form and sufficiency by James D. Stokes, City Attorney.