Placement: Public Hearing - Quasi Judicial
Action Requested: Motion / Vote
title
P21-012 Southern Grove Development of Regional Impact (DRI) Amendment - 8th Amendment
Location: West of Interstate 95, between Tradition Parkway and the C-23 Canal and bordered to the west by SW Community Boulevard.
Legal Description: A parcel of land lying in Sections 15, 22, 23, 26, 27, 34, and 35 Township 37 South, Range 39 East, St. Lucie County, Florida
A request to amend the Southern Grove DRI by amending Exhibit “1”, General Conditions of Approval, Exhibit “B”, Master Development Plan (Map H and Map H-2), Exhibit “D”, Conversion Matrix, And Exhibit “E”, DRI Trip Generation Rates.
body
Submitted By: Bridget Kean, AICP, Senior Planner
Executive Summary: Mattamy Palm Beach, LLC, and the Port St. Lucie Governmental Finance Corporation have applied to amend the development order for the Southern Grove Development of Regional Impact (DRI) by amending Exhibit “1”, General Conditions of Approval, Exhibit “B” to Exhibit “1”, Master Development Plan (Map H and Map H-2), Exhibit “D” to Exhibit “1”, Conversion Matrix, and Exhibit “E” to Exhibit “1”, DRI Trip Generation Rates. The proposed changes are based on the recommendations included in the Southern Grove Master Plan. The Southern Grove Master Plan was approved by the City Council on February 25, 2021.
Presentation Information: Staff will provide a presentation.
Staff Recommendation: Move that the Board recommend approval of the proposed amendment.
Alternate Recommendations:
1. Move that the Board amend the recommendation and recommend approval of the proposed amendment.
2. Move that the Board not recommend approval.
Background: Southern Grove is an approved Development of Regional Impact (DRI) that is located west of Interstate 95, south of Tradition Parkway, north of the C-23 canal and approximately 3,606 acres in size. In June 2018, the City of Port St. Lucie acquired approximately 1,183 acres of land within the Southern Grove DRI. The land was deeded to and is managed by the Port St. Lucie Governmental Finance Corporation (GFC). In October 2019, the City engaged the Treasure Coast Regional Planning Council (TCRPC) to create an updated land development and infrastructure master plan for the city owned land in Southern Grove including a financial and market analysis, review of competitive markets, and strategies for property disposition. Based on a review of market conditions, the Southern Grove Master Plan recommended changes to the development program for Southern Grove including a re-organization of the land use subdistricts, modifications to the DRI development entitlements, and modifications to infrastructure improvements to produce a more economically viable development program for Southern Grove.
Issues/Analysis: See attached staff report.
Special Consideration: N/A
Location of Project: The property is generally located west of Interstate 95, between Tradition Parkway and the C-23 Canal and bordered to the west by SW Community Boulevard.
Attachments:
1. Staff Report
2. Attachment “A” Proposed Southern Grove DRI Amendment
3. Application
4. Public Works Traffic Memo
5. Third Party Consultant Review of Traffic Study
6. 2021 Southern Grove Traffic Study
7. Warranty Deed (Mattamy)