File #: 2025-375    Version: 1 Name:
Type: Consent Status: Passed
File created: 4/9/2025 In control: City Council
On agenda: 5/12/2025 Final action: 5/12/2025
Title: Approve Amendment #12 to Contract #20200077 for the Construction of Port St. Lucie Blvd. North Roadway Project.
Attachments: 1. Amendment_#12_signed., 2. Amendment #12 backup documentation., 3. Amendment #11., 4. Amendment #10., 5. Amendment #9., 6. Amendment #8., 7. Amendment #7., 8. Amendment #6., 9. Amendment #5., 10. Amendment #4., 11. Amendment #3., 12. Amendment #2., 13. Amendment #1., 14. Original Contract.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Placement: Consent Agenda                     

Action Requested: Motion / Vote                     

title

Approve Amendment #12 to Contract #20200077 for the Construction of Port St. Lucie Blvd. North Roadway Project.

body

 Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

 

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

 

Summary Brief (Agreements/Contracts only)

1.                     Prepared by: Robyn Holder, CPPB (PMD).

2.                     Parties: City of Port St. Lucie and Zahlene Enterprises, Inc.

3.                     Purpose: To provide compensation for unforeseen utility conflicts needed to complete the project.

4.                     New/Renewal/Modified: Modified.

5.                     Duration: The initial term began on 9/27/2021 through 3/21/2023. Through several Amendments the time has been extended through 6/6/2025. No additional time is needed for this Amendment.

6.                     Benefits to Port St. Lucie: This project will provide additional intersection capacity, accessible multi-use pathways, pedestrian lighting, underground drainage, and upgraded water and sewer facilities.

7.                     Cost to Port St. Lucie (Annual and Potential): An additional $725,826.93 is needed for the unforeseen utility work for a new Contract amount of $8,984,469.47.

 

Presentation Information: N/A.

 

Staff Recommendation: Move that the Council approve Amendment #12 to Contract #20200077 for the Construction of Port St. Lucie Blvd. North Roadway Project with Zahlene Enterprises, Inc.

 

Alternate Recommendations:

1.                     Move that the Council amend the recommendation and approve Amendment #12 to Contract #20200077.

2.                     Move that the Council not approve Amendment #12 to Contract #20200077 and provide staff with direction.

 

Background: On September 23, 2021, the City entered into a Contract with Zahlene Enterprises, Inc. for the construction services described above. The Contract commenced on September 27, 2021, and originally terminated 540 calendar days later on March 21, 2023. The original Contract amount was $8,006,338.18.

 

Amendment #12 incorporates Change Order No. 15 which has been created to combine multiple potential change orders (14, 21, 22, 23, 24, 25, 26, 27 and 28) for extra work due to multiple unforeseen utility conflicts with the 16” force main and 8” gas main, and 16” by-pass at Station 269. Also, compensation for additional work to incorporate fully accessible pedestrian system push buttons at the intersections of Darwin Blvd. and Aurelia, and to compensate for additional work due to incorporating a preemptive glance system at the same intersection. 

 

Issues/Analysis: Staff has reviewed these changes and has received FDOT concurrence to approve the unforeseen scope of work. Staff is recommending approval.

                     

Financial Information: Funds are appropriated in the Road & Bridge CIP / Traffic / Improvements O/T Building/ SW PSL Blvd. Reconstruction (301-4121-563000-Y1717).

 

Special Consideration: N/A.

 

Location of Project: SW Port St. Lucie Blvd. west of Gatlin Blvd.

 

Attachments:

1.                     Amendment #12 signed.

2.                     Amendment #12 backup documentation.

3.                     Amendment #11.

4.                     Amendment #10.

5.                     Amendment #9.

6.                     Amendment #8.

7.                     Amendment #7.

8.                     Amendment #6.

9.                     Amendment #5.

10.                     Amendment #4.

11.                     Amendment #3.

12.                     Amendment #2.

13.                     Amendment #1.

14.                     Original Contract.

 

NOTE: All of the listed items in the “Attachment” section above are in the custody of the City Clerk. Any item(s) not provided in City Council packets are available upon request from the City Clerk.

 

Internal Reference Number: 25099-08.

 

Legal Sufficiency Review: 

Reviewed by Alyssa Lunin, Deputy City Attorney. Approved as to Legal form and sufficiency by Richard Berrios, City Attorney.