File #: 2020-964    Version: 1 Name:
Type: Resolution Status: Passed
File created: 11/23/2020 In control: City Council
On agenda: 12/14/2020 Final action: 12/14/2020
Title: Resolution 20-R133, A Resolution Approving and Accepting a Preliminary Subdivision Plat with Construction Plans for Tradition Parkway-Western Grove (P20-143)
Attachments: 1. Resolution, 2. Preliminary Plat, 3. Construction Plans, 4. Landscape Plans, 5. Staff Report, 6. Application, 7. Staff Presentation

Placement: Resolutions                     

Action Requested: Motion / Vote                     

title

Resolution 20-R133, A Resolution Approving and Accepting a Preliminary Subdivision Plat with Construction Plans for Tradition Parkway-Western Grove (P20-143)  

body

Submitted By: Bridget Kean, AICP, Senior Planner

 

Strategic Plan Link: The City’s Mission to plan for smart and balanced growth.

 

Executive Summary (General Business): Mattamy Palm Beach, LLC, as the developer of the Western Grove Development of Regional Impact (DRI), has submitted an application for preliminary subdivision plat approval with construction plans to extend Tradition Parkway from its current terminus at the Renaissance Charter School in Tradition an additional 4,161 linear feet west to an FPL powerline easement in the Western Grove DRI.  The parkway extension will provide access to a proposed single -family residential subdivision known as Western Grove 1-Emry (P20-196) and the city owned Tradition Regional Park site.  

 

Presentation Information: Staff may provide a short presentation.

 

Staff Recommendation: Move that the Council adopt the resolution as recommended by the Site Plan Review Committee. 

 

Alternate Recommendations:

1.                     Move that the Council amend the recommendation and adopt the resolution. 

2.                     Move that the Council not adopt the resolution and provide staff direction. 

 

Background: The Site Plan Review Committee recommended approval of the proposed preliminary subdivision plat with construction plans at their meeting on November 4, 2020. 

 

Issues/Analysis: As outlined in the development order for the Western Grove DRI, Mattamy Palm Beach, LLC, is the entity responsible for the construction of Tradition Parkway.  The roadway will be designed as 130- foot wide roadway and include Tradition Trail.  The typical cross section for Tradition Trail depicts a ten (10) foot multi-use path and a separate twelve (12) foot golf cart path.   

                     

Financial Information: N//A 

 

Special Consideration: N/A

 

Location of Project: The project is generally located west of Interstate 95, east of Range Line Road, south of the proposed extension of Crosstown Parkway and north of the Discovery Way right-of-way.

 

Attachments:

1.                     Resolution

2.                     Preliminary Plat

3.                     Construction Plans

4.                     Landscape Plans

5.                     Staff Report

6.                     Application

7.                     Staff Presentation

 

NOTE: All of the listed items in the “Attachment” section above are in the custody of the City Clerk. Any item(s) not provided in City Council packets are available upon request from the City Clerk.

 

Internal Reference Number: 5140

 

Legal Sufficiency Review: 

Reviewed by Elizabeth L. Hertz, Deputy City Attorney. Approved as to Legal form and sufficiency by James D. Stokes, City Attorney.