Legislation Details

File #: 2026-607    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 6/24/2026 In control: City Council
On agenda: 8/24/2026 Final action:
Title: Resolution 26-R65, Authorizing the City Manager to Enter into and Execute Supplemental Agreement No. 1 with the State of Florida Department of Transportation, that Proposes to Reduce the Amount of Federal Funding Assistance for the Project to $0.00 Concerning the Construction Required to Make Intersection Improvements on Southwest Gatlin Boulevard at Southwest Savona Boulevard.
Attachments: 1. 453495-1 SA-01_ Supplemental Agreement No. 1, 2. Project Map_Gatlin & Savona Int. Improvements, 3. Resolution 24-R_Council Resolution_Gatlin at Savona Intersection
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Placement: Resolutions                     

Action Requested: Motion / Vote                     

title

Resolution 26-R65, Authorizing the City Manager to Enter into and Execute Supplemental Agreement No. 1 with the State of Florida Department of Transportation, that Proposes to Reduce the Amount of Federal Funding Assistance for the Project to $0.00 Concerning the Construction Required to Make Intersection Improvements on Southwest Gatlin Boulevard at Southwest Savona Boulevard. 

body

 Submitted By: Emily Seitter, CIP Administrator, CIP & Half-Cent Sales Tax Projects, Public Works

 

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

 

Summary Brief (Agreements/Contracts only)

1.                     Prepared by: Emily Seitter, Public Works

2.                     Parties: City of Port St. Lucie and Florida Department of Transportation (FDOT)

3.                     Purpose: To enter into Supplemental Agreement No. 1

4.                     New/Renewal/Modified: New

5.                     Duration: N/A

6.                     Benefits to Port St. Lucie: Adoption of this supplemental agreement will allow for the congestion management improvements at the intersection of SW Gatlin Boulevard and SW Savona Boulevard to proceed as a City-funded project.

7.                     Cost to Port St. Lucie (Annual and Potential): N/A

 

Presentation Information: Staff will be available to answer any questions.

 

Staff Recommendation: Move that the Council approve Supplemental Agreement No. 1

 

Alternate Recommendations:

1.                     Move that the Council amend the recommendation and approve the acquisition.

2.                     Move that the Council not approve the recommendation and provide staff direction.

 

Background: In 2024, the City entered into a local agency program funding agreement with the Florida Department of Transportation (FDOT) for the improvements and extension of existing turn lanes as part of Phase 1 Intersection Improvements at SW Gatlin Boulevard at SW Savona Boulevard. Subsequently, it has been determined by the City and FDOT to no longer fund the project through the LAP Agreement in order to provide a singular procurement for the construction of the project and to improve the project outcome for City residents.

 

Issues/Analysis: The Resolution authorized the City Manager, or his designee, to enter into  Supplemental Agreement No. 1 with FDOT and allows City Staff to take actions necessary to implement the terms and conditions of the agreement.

                     

Financial Information: This project will be funded exclusively through local funding and is currently budgeted.

 

Special Consideration: N/A

 

Location of Project: East and west bound turn lanes on southwest Gatlin Boulevard, located at the intersection of southwest Gatlin Boulevard and southwest Savona Boulevard

 

Attachments: 1. Supplemental Agreement No. 1

2. Resolution

3. Location Map

 

NOTE: All of the listed items in the “Attachment” section above are in the custody of the City Clerk. Any item(s) not provided in City Council packets are available upon request from the City Clerk.

 

Internal Reference Number: 26146-07

 

Legal Sufficiency Review: 

Reviewed by Russell Ward, Deputy City Attorney. Approved as to Legal form and sufficiency by Richard Berrios, City Attorney.