City of Port St. Lucie header
File #: 2022-494    Version: 1 Name:
Type: Resolution Status: Passed
File created: 6/1/2022 In control: City Council
On agenda: 6/13/2022 Final action: 6/13/2022
Title: Resolution 22-R70, A Resolution Approving the Preliminary and Final Plat with Construction Plans for Telaro at Southern Grove Phases 2 and 3. (P21-244)
Attachments: 1. Resolution, 2. Preliminary and Final Plat, 3. Landscape Plans, 4. Construction Plans, 5. Staff Report, 6. Public Works Memo, 7. Staff Presentation
Placement: Resolutions
Action Requested: Motion / Vote
title
Resolution 22-R70, A Resolution Approving the Preliminary and Final Plat with Construction Plans for Telaro at Southern Grove Phases 2 and 3. (P21-244)
body
Submitted By: Laura H. Dodd, AICP

Strategic Plan Link: The City's Mission to plan for smart and balanced growth.

Executive Summary (General Business): An application for preliminary and final subdivision plat and construction plan approval for Telaro at Southern Grove Phase 2-3. The project consists of 257 single-family lots, a conservation tract, water management tracts, private road right of way, and other associated infrastructure improvements upon 87.8 acres.

Presentation Information: Staff may provide a brief presentation.

Staff Recommendation: Move that the Council approve the request with conditions.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve the request with conditions.
2. Move that the Council not approve and provide staff direction.

Background: The preliminary and final plat was approved by SPRC on February 23, 2022.

Issues/Analysis: See staff report.

Financial Information: n/a

Special Consideration: Staff is recommending approval with the guidance of imposing one of the two transportation improvement conditions expressed in the traffic analysis, or as Council determines acceptable based upon their deliberations. If Council deliberations provide for a condition of approval, an updated resolution outlining these provisions shall be drafted for immediate execution.

Location of Project: South of Discovery Way, East of SW Community Blvd., and West of SW Village Park Way

Attachments: 1. Resolution 2. Preliminary and Final Plat 3. Landscape Plans 4. Construction Plans 5. Public Works Memo 6. Staff Report 7. Staff Presentation

NOTE: All of the listed items in the "Attachment" section above are in the custody of the City Clerk. Any item(s) not provided in City Council packe...

Click here for full text