File #: 2026-046    Version: 1 Name:
Type: Consent Status: Consent
File created: 12/23/2025 In control: City Council
On agenda: 1/12/2026 Final action:
Title: Approve Amendments #16 & #17 to Contract #20190112 for the Design & Permitting Services for the Floresta Drive Improvement Project Phases 2 & 3.
Attachments: 1. 20190112-06 Amendment #17 signed_12-23-2025, 2. 20190112-06 Amendment #16 signed_12-23-2025, 3. 20190112-05-A15, 4. 20190112-05-A14, 5. 20190112-05-A13, 6. 20190112-05-A12, 7. 20190112-05-A11, 8. 20190112-05-A10, 9. 20190112-05-A9, 10. 20190112-05-A8, 11. 20190112-05-A7, 12. 20190112-05-A6, 13. 20190112-05-A5, 14. 20190112-05-A4, 15. 20190112-05-A3, 16. 20190112-05-A2, 17. 20190112-05-A1, 18. 20190112-05
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendments #16 & #17 to Contract #20190112 for the Design & Permitting Services for the Floresta Drive Improvement Project Phases 2 & 3.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and CONSOR North America, Inc. fka CONSOR Engineers, LLC fka American Consulting Engineers of Florida, LLC ("CONSOR").
3. Purpose: Amendment #16 - Additional engineering funds are requested to design Water Main (WM) replacements in coordination with the ongoing Phase 3 construction. Amendment #17 - This Amendment is needed to increase in funds for design due to AT&T conflicts.
4. New/Renewal/Modified: Modified.
5. Duration: No additional days are needed for these Amendments. The end date remains 11/19/2027.
6. Benefits to Port St. Lucie: Replacement of aging pipelines alongside the roadway construction path and enter into a separate agreement to reimburse the City due to the AT&T conflicts.
7. Cost to Port St. Lucie (Annual and Potential): Amendment #16 requires an increase of $99,050.00. Amendment #17 requires an increase of $201,521.00. The new Contract amount is $3,246,573.00.

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve Amendments #16 & #17 to Contract #20190112 for the Design & Permitting Services for Floresta Drive Improvement Project Phases 2 & 3 with CONSOR.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendments #16 & #17 to Contract #20190112.
2. Move that the Council not approve Amendments #16 & #17 to Contract #20190112 and provide staff with direction.

Background: Amendment #16 - The City's Public Works Department is currently reconstructing Floresta Drive between Crosstown ...

Click here for full text