File #: 2025-116    Version: 1 Name:
Type: Consent Status: Passed
File created: 1/27/2025 In control: City Council
On agenda: 2/10/2025 Final action: 2/10/2025
Title: Ratify Amendments #2 Through #4 and Approve Amendment #5 to Contract #20230077 for the Construction of Anthony F. Sansone Sr. Blvd. Phase 3 Extension.
Attachments: 1. 20230077-06 Amendment #5 signed, 2. 20230077-05-A4, 3. 20230077-05-A3, 4. 20230077-05-A2, 5. 20230077-05-A1, 6. 20230077-05
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Ratify Amendments #2 Through #4 and Approve Amendment #5 to Contract #20230077 for the Construction of Anthony F. Sansone Sr. Blvd. Phase 3 Extension.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and J.W. Cheatham, LLC.
3. Purpose: To account for design changes.
4. New/Renewal/Modified: Modify.
5. Duration: The end date last approved by Council was November 30, 2024, in Amendment #1. Amendments #2- #4 have extended the end date to April 3, 2025. Amendment #5 does not add any additional time.
6. Benefits to Port St. Lucie: The construction of Anthony F. Sansone Sr. Blvd. Phase 3 Extension will continue the overall development of the Legacy Park at Tradition Center for Commerce.
7. Cost to Port St. Lucie (Annual and Potential): An additional $168,901.17 for Amendment #2, $0 Amendment #3 (time extension only), $0 Amendment #4 (time extension only), and $645,364.05 for Amendment #5 for a total Contract amount of $11,771,360.45.

Presentation Information: N/A.

Staff Recommendation: Move that the Council ratify Amendments #2 through #4 and approve Amendment #5 to Contract #20230077 for the Construction of Anthony F. Sansone Sr. Blvd. Phase 3 Extension with J.W Cheatham, LLC.

Alternate Recommendations:
1. Move that the Council amend the recommendation and ratify Amendments #2 through #4 and approve Amendment #5 to Contract #20230077.
2. Move that the Council not ratify Amendments #2 through #4 and approve Amendment #5 to Contract #20230077 and provide staff with direction.

Background: The City Council identified the development of the Southern Grove Master Plan to meet the goals of a diverse local economy and employment opportunities with the initiative of bui...

Click here for full text