File #: 2023-073    Version: 1 Name:
Type: Consent Status: Passed
File created: 1/5/2023 In control: City Council
On agenda: 1/9/2023 Final action: 1/9/2023
Title: Approve Amendment #1 to Contract #20220045 for the Construction of the Floresta Drive Improvement Project Phase II.
Attachments: 1. 20220045-06 -A1 Amendment #1, 2. 20220045-05
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendment #1 to Contract #20220045 for the Construction of the Floresta Drive Improvement Project Phase II.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Department (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Felix Associates of Florida, Inc.
3. Purpose: To incorporate redesign of the bridge piles/substructure to facilitate single-phase bridge construction within six (6) months.
4. New/Renewal/Modified: Modified.
5. Duration: No additional calendar days are required.
6. Benefits to Port St. Lucie: To insure bridge construction in a timely manner.
7. Cost to Port St. Lucie (Annual and Potential): Net deduction of ($240,726.00) for a new contract amount of $29,756,448.23.

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve Amendment #1 to Contract #20220045 for the Construction of the Floresta Drive Improvement Project Phase II with Felix Associates of Florida, Inc.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendment #1 to Contract #20220045.
2. Move that the Council nor approve Amendment #1 to Contract #20220045 and provide staff with direction.

Background: On 7/25, 2022, City Council approved Contract #20220045 for Floresta Drive Improvements Project Phase II in the amount of $29,997,174.23. Improvements to the Floresta Drive corridor is a priority of the City Council. The improvements include both a two-lane section with landscaped medians and a two-lane section with a bi-directional turn lane. Both sections include sidewalks, bike lanes, curb and gutter, landscaping, irrigation, water and sewer adjustments and pedestrian lighting. This phase also includes a bridge replacement and removal of an existing pedestrian b...

Click here for full text