File #: 2022-481    Version: 1 Name:
Type: Consent Status: Passed
File created: 5/24/2022 In control: City Council
On agenda: 6/13/2022 Final action: 6/13/2022
Title: Approve Amendment #2 to Contract #20200070 for the Construction of Roadway Improvements on Port St. Lucie Boulevard North (Segment 3).
Attachments: 1. 20200077-06 Amendment #2 JMZ, 2. Contract #20200077, 3. 20200077--Amendment #1
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendment #2 to Contract #20200070 for the Construction of Roadway Improvements on Port St. Lucie Boulevard North (Segment 3).
body
Submitted By: Robyn Holder, CPPB, Procurement Management Department (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Zahlene Enterprises, Inc.
3. Purpose: To change specifications on required Mast Arms.
4. New/Renewal/Modified: Modified.
5. Duration: No additional time is required.
6. Benefits to Port St. Lucie: To match existing materials along the corridor for a more cohesive appearance.
7. Cost to Port St. Lucie (Annual and Potential): One-time increase of $17,904.30. Amendment #1 has already been approved at $8,790.25 which did not require Council approval. The addition of Amendment #2 exceeds $25,000.00 and requires Council approval.

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve Amendment #2 to Contract #20200077 with Zahlene Enterprises, Inc. in the amount of $17,904.30.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendment #2 to Contract #2020007.
2. Move that the Council not approve Amendment #2 to Contract #2020007 and provide staff with direction.

Background: The existing 4-lane divided highway is currently under construction to create a fully "urban" roadway to include curb and gutter, multi-use paths, landscaping, irrigation roadway lighting and pedestrian lighting that will match what is being constructed by the Florida Department of Transportation (FDOT). To maintain continuity, the City has requested that the mast arms be changed to the 12-sided mast arms. This results in a price difference of $17,904.30.

Issues/Analysis: Staff has reviewed the additional expense and finds it reasonable an...

Click here for full text