File #: 2023-540    Version: 1 Name:
Type: Consent Status: Passed
File created: 6/8/2023 In control: City Council
On agenda: 6/26/2023 Final action: 6/26/2023
Title: Approve Amendment #1 to Contract #20230005 for Mechanical Integrity Testing for Southport and Westport Injection Wells.
Attachments: 1. 20230005 -Amendment #1, 2. Original Contract
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendment #1 to Contract #20230005 for Mechanical Integrity Testing for Southport and Westport Injection Wells.
body
Submitted By: India Barr, Procurement Management Department (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: India Barr, Procurement Agent 1.
2. Parties: City of Port St. Lucie and Layne Christensen Company.
3. Purpose: To provide the required Mechanical Integrity Testing (MIT) at the Glades Wastewater Treatment Facility, IW-1 Deep Injection Well.
4. New/Renewal/Modified: Modified.
5. Duration: Additional 62 calendar days are required for the testing of Glades Deep Injection Well. New end date is 8/31/2023.
6. Benefits to Port St. Lucie: As specified in Rule 62-528, Florida Administrative Code (FAC) a Class I injection well must demonstrate mechanical integrity every five years.
7. Cost to Port St. Lucie (Annual and Potential): An additional $53,550.00 will be added to the original Contract. The new Contract amount is $204,750.00.

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve Amendment #1 to Contract #20230005 for the additional MIT testing services.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendment #1 to Contract #20230005.
2. Move that the Council not approve Amendment #1 to Contract #20230005 and provide staff with direction.

Background: As specified in Rule 62-528, Florida Administrative Code (FAC) a Class 1 injection well must demonstrate mechanical integrity every five years. The most recent casing pressure test for the Glades Deep Injection Well IW-1 was last completed in September 2018. Therefore, the next MIT must be completed by September 2023.

Issues/Analysis: Due to the limited number of contractors that can perform this type of work, the Department is requesti...