Award Contract # 20230067R for East Torino Parkway Improvements Project.
body
Submitted By: India Barr , Procurement Contracting Officer I.
Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.
Summary Brief (Agreements/Contracts only)
1. Prepared by: India Barr ,Procurement Contracting Officer I.
2. Parties: City of Port St. Lucie and Timothy Rose Contracting Inc.
3. Purpose: To construct a roundabout at the intersection of East Torino Parkway and Turtle Dove Lane/North Torino Parkway. The intersection is currently operating as an "All Way" stop. The project also includes improvements at the intersection of East Torino Parkway at Midway Road. These improvements include adding an additional left turn lane and lengthening the existing left turn/through lane and right turn lane.
4. New/Renewal/Modified: New.
5. Duration: 270 calendar days with no option to renew.
6. Benefits to Port St. Lucie: Reduce traffic congestion and improve traffic flow. The roundabout will also create a "Gateway" into the City with the potential installation of an art feature.
7. Cost to Port St. Lucie (Annual and Potential): One- time expense of $2,185,781.55.
Presentation Information: N/A.
Staff Recommendation: Move that the Council award Contract #20230067R and enter into a unit price contract with Timothy Rose Contracting Inc. for the East Torino Parkway Improvements Project.
Alternate Recommendations:
1. Move that the Council amend the recommendation and award Contract #20230067R.
2. Move that the Council not award Contract #20230067R and provide staff with direction.
Background: The increase of traffic on East Torino Parkway has restricted traffic from North Torino Parkway and Turtle Dove Lane from being able to access East Torino Parkway, thus prompting the installation of an "All Way" stop at the intersection. While this improved access to East Torino Parkway, it also increas...