File #: 2022-788    Version: 1 Name:
Type: Consent Status: Passed
File created: 8/30/2022 In control: City Council
On agenda: 9/12/2022 Final action: 9/12/2022
Title: Award Contract #20210040R for the Alcantarra Boulevard Sidewalk Construction Project.
Attachments: 1. Alcantarra Blvd Location Map, 2. 20210040R-08 E-Bid Tabulation Report, 3. Notice of Intent to Award- NOIA (Legistar Posting), 4. 20210040R-05 signed by McTeague, 5. Recommended Proposal - McTeague, 6. 20210040R - E-Bid Document -FINAL, 7. Attachment G - Roadway Plans 6-3-2022
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Award Contract #20210040R for the Alcantarra Boulevard Sidewalk Construction Project.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Department (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and McTeague Construction Co., Inc.
3. Purpose: To construct 4,197.97 LF of six (6') foot wide concrete sidewalk on the south side of Alcantarra Blvd.
4. New/Renewal/Modified: New.
5. Duration: 150 calendar days.
6. Benefits to Port St. Lucie: Provide a safe interconnected sidewalk network for the citizens of the City
7. Cost to Port St. Lucie (Annual and Potential): One-time expense of $463,225.48.

Presentation Information: N/A.

Staff Recommendation: Move that the Council award Contract #20210040R and enter into a unit price contract with McTeague Construction Co., Inc. for the construction of the Alcantarra Blvd. Sidewalk Project.

Alternate Recommendations:
1. Move that the Council amend the recommendation and award Contract #20210040R.
2. Move that the Council not award Contract #20210040R and provide staff with direction.

Background: Since 2006, the City has prioritized the design and construction of sidewalks citywide. The original areas were in the proximity of schools, especially elementary schools to provide a safe route to school for children. Alcantarra Blvd. is on the 10-year Sidewalk Master Plan list approved by the City Council. The City has received funding through the Florida Department of Transportation (FDOT) Local Agency Program (LAP) Grant to construct the sidewalks.

An E-Bid was issued on June 9, 2022 to 1,574 potential suppliers. There were 33 plan holders with 4 proposals being received on July 19, 2022.

Issues/Analysis: Staff has reviewed the proposals and has determined that McTeague Constructio...

Click here for full text