Title: Award Contract #20220009 for the Rosser Boulevard Sidewalk Construction Project.
Attachments: 1. 20220009 Attachment B - Location Map, 2. Notice of Intent to Award- NOIA, 3. 20220009-08 E-Bid Tabulation Report, 4. 20220009-05 Contract, 5. McTeague Construction Bid Package, 6. 20220009 - E-Bid Document, 7. 20220009 Attachment A - ROSSER BLVD SIDEWALK - 100% CONSTRUCTION PLANS
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Award Contract #20220009 for the Rosser Boulevard Sidewalk Construction Project.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Department (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and McTeague Construction Co., Inc.
3. Purpose: To construct approximately 6,160 linear feet of 6-foot-wide concrete sidewalk on the west side of Rosser Boulevard.
4. New/Renewal/Modified: New.
5. Duration: 180 calendar days with no option to renew.
6. Benefits to Port St. Lucie: Provide high quality infrastructure & facilities for the use of all residents.
7. Cost to Port St. Lucie (Annual and Potential): One-time expense of $559,709.

Presentation Information: N/A.

Staff Recommendation: Move that the Council award Contract #20220009 and enter into a unit price contract with McTeague Construction Co., Inc. for the Rosser Boulevard Sidewalk Construction Project.

Alternate Recommendations:
1. Move that the Council amend the recommendation and award Contract #20220009.
2. Move that the Council not approve Contract #20220009 and provide staff with direction.

Background: Since 2006, the City has prioritized the design and construction of sidewalks citywide. The original areas were in proximity to schools, especially elementary schools to provide a safe route to school for children. The list has since expanded to establish a network of connecting sidewalks throughout the City. Rosser Blvd is on the Sidewalk Priority List approved by City Council. This project is funded by the 1/2 cent Sales Tax.

An E-Bid was issued on October 30, 2021 to 1,392 potential suppliers. There were 27 plan holders with 2 proposals being received. All proposals were deemed responsive.

Issues/Analysis: Staff has reviewed the proposals and finds that McTeag...