City of Port St. Lucie header
File #: 2024-1223    Version: 1 Name:
Type: Consent Status: Consent
File created: 11/25/2024 In control: City Council
On agenda: 12/9/2024 Final action:
Title: Award Contract #20240172 for Floresta Drive Phase 3 CEI and Geotechnical Services.
Attachments: 1. Notice of Intent to Award., 2. Contract_20240172_FINAL (Signed), 3. Recommended Proposal from Culpepper & Terpening., 4. eRFP Documents.
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Award Contract #20240172 for Floresta Drive Phase 3 CEI and Geotechnical Services.
body
Submitted By: Alaina Knofla, Procurement Contracting Officer III, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Alaina Knofla, Procurement Contracting Officer III (PMD).
2. Parties: City of Port St. Lucie and Culpepper & Terpening, Inc.
3. Purpose: Public Works Department seeking approval of Culpepper & Terpening, Inc. to provide Construction Engineering and Inspection (CEI) & Geotechnical (GEO) services for Floresta Drive Improvements Phase 3 Project.
4. New/Renewal/Modified: New.
5. Duration: This contract will terminate one thousand one hundred and fifty-five (1,155) calendar days after it is awarded. There are no renewals for this contract.
6. Benefits to Port St. Lucie: The project will complete the construction of Floresta Drive from Crosstown Parkway to Prima Vista Boulevard as a complete street providing bike lanes, sidewalks, traffic calming, streetlights, and landscape.
7. Cost to Port St. Lucie (Annual and Potential): Budgeted Expenditures not to exceed $5,616,117.20.

Presentation Information: N/A.

Staff Recommendation: Move that the Council award Contract #20240172 to Culpepper & Terpening, Inc.

Alternate Recommendations:
1. Move that the Council reject the recommended award and provide staff with direction.
2. Move that the Council reject all proposals and provide staff with direction to re-solicit or cancel the Request for Proposals.

Background: Improvements to the Floresta Drive corridor are a priority for the City Council and at the 2017 Summer Retreat, Council directed staff to model the corridor from a traffic standpoint for both a 2-lane and 4-lane roadway section. The new modeling was performed, and it included the new Crosstown Parkway Ex...