Placement: Consent Agenda
Action Requested: Motion / Vote
title
Ratify Amendment #5 and Approve Amendment #6 to Contract #20230117 for CEI & GEO Services for the Port St. Lucie Blvd. Segment 3 Project.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).
Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.
Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Johnson, Mirmiran & Thompson, Inc. ("JMT").
3. Purpose: To provide an increase in funding and time for the CEI & GEO Services to align contract funding & time with the anticipated total contract time for the construction.
4. New/Renewal/Modified: Modified.
5. Duration: An additional 49 calendar days for a new end date of September 18, 2025.
6. Benefits to Port St. Lucie: The Port St. Lucie Blvd. Segment 3 Project will provide additional intersection capacity, accessible multi-use pathways, pedestrian lighting, underground drainage, and upgraded water and sanitary facilities.
7. Cost to Port St. Lucie (Annual and Potential): An additional $170,736.00 for a new Contract amount of $1,539,485.00.
Presentation Information: N/A.
Staff Recommendation: Move that the Council ratify Amendment #5 and approve Amendment #6 to Contract #20230117 for the CEI & GEO Services for the Port St. Lucie Blvd. Segment 3 Project with Johnson, Mirmiran & Thompson, Inc.
Alternate Recommendations:
1. Move that the Council amend the recommendation and ratify Amendment #5 and approve Amendment #6 to Contract #20230117.
2. Move that the Council not ratify Amendment #5 nor approve Amendment #6 to Contract #20230117 and provide staff with direction.
Background: On September 12, 2023, the City of Port St. Lucie executed a contract with JMT for CEI & GEO Services for the above referenced project. The contract commenced on September 12, 2023, and originally terminated 200 calendar days thereafter on March 3...
Click here for full text