Title: Resolution 25-R60, Authorizing the Final Acceptance of Public Roadway Improvements for Southern Grove Plat No. 44 (P23-072) Constructed by Mattamy Palm Beach, LLC
Attachments: 1. 1. Resolution.pdf, 2. 2. Owners Affidavit, 3. 3. Contractor's Affidavit, 4. 4. Bill of sale, 5. 5. Cost Estimate - Maintenance Bond, 6. 6. Maintenance Bond, 7. 7. Owners Warranty, 8. 8. Contractors Warranty, 9. 9. Roadway Turnover Request Letter, 10. 10. Landscape Certification, 11. 11. Irrigation Certification, 12. 12. Recorded Plat, 13. 13. Location Map, 14. 13. Request for Roadway Turnover Memo, 15. 14. Substantial Completion Inspections for Roadway Turnover
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Placement: Resolutions
Action Requested: Motion / Vote
title
Resolution 25-R60, Authorizing the Final Acceptance of Public Roadway Improvements for Southern Grove Plat No. 44 (P23-072) Constructed by Mattamy Palm Beach, LLC
body
Submitted By: Diana Spriggs, P.E., Assistant Director, Public Works

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Executive Summary (General Business): Mattamy Palm Beach, LLC has completed the construction of the initial two lanes of Southern Grove Plat No. 44 (P23-072) as approved by City Council. The developer has requested the City accept ownership and maintenance of the roadway improvements in accordance with City Code of Ordinance Section 156.150.

Presentation Information: Staff will be available to answer questions.

Staff Recommendation: Move that the Council accept the roadway improvements in accordance with Section 156.150 of the City Code of Ordinances.

Alternate Recommendations:
1. Move that the Council amend the recommendation and accept the roadway improvements.
2. Move that the Council not accept the roadway improvements and provide staff direction.

Background: Developer entered into the Becker Road Construction Agreement ("Agreement") with the City of Port St. Lucie on February 14, 2022. The Agreement obligated Developer to construct 6,148 linear feet of Becker Road from just west of the Community Blvd intersection to approximately 30 feet west of the start of the turn lanes for the Village Parkway intersection. According to the Agreement, Completion of Construction must occur within 12 months of the Developer receiving all permits and approvals for construction. The Agreement defines Completion of Construction as (i)a written Certificate of Completion issued by the EOR of record to the City, (ii) a final walk-through and acceptance by the City of the Mattamy road section in accordance with Section 156.150 of the City Code, and (iii) Mattamy's posting of a one year mai...

Click here for full text