Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Additional Expenditure under Contract #20250315 for the Purchase and Installation of a Replacement Chiller at the MIDFLORIDA Event Center.
body
Submitted By: Kevin Eggleston, Procurement Contracting Officer I, Procurement Management Division (PMD).
Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.
Summary Brief (Agreements/Contracts only)
Prepared by: Kevin Eggleston, Procurement Contracting Officer I, PMD.
Parties: City of Port St. Lucie and TRANE U.S. Inc. (“Trane”).
Purpose: To approve additional expenditure under Contract #2025315 for the replacement of the existing CH-1 chiller at the MIDFLORIDA Event Center with a new 200-ton Trane air-cooled chiller.
New/Renewal/Modified: N/A.
Duration: Contract #20250315, utilizing OMNIA Cooperative Contract #3341, is in effect through August 31, 2027, with one (1) additional five-year renewal option.
Benefits to Port St. Lucie: Ensures reliable and efficient HVAC operation at the MIDFLORIDA Event Center, supporting both Event Center and Parks & Recreation operations and their continued service to City residents.
Cost to Port St. Lucie (Annual and Potential): This approval is requested to provide for a one-time expenditure of $429,359.00 for the replacement and installation of the CH-1 chiller at the MIDFLORIDA Event Center. Including previously approved expenditures under Contract #20250315, the total approved expenditures under the Contract will increase to $2,744,379.00.
Presentation Information: N/A.
Staff Recommendation: Move that the Council approve the additional expenditure under Contract #20260315, in the amount of $429,395.00 for the MIDFLORIDA Event Center CH-1 chiller replacement and installation.
Alternate Recommendations:
Move that the Council amend the recommendation and approve the additional expenditure under Contract #20250315.
Move that the Council not approve the additional expenditure...