File #: 2024-511    Version: 1 Name:
Type: Consent Status: Passed
File created: 5/14/2024 In control: City Council
On agenda: 5/28/2024 Final action: 5/28/2024
Title: Approve Amendment #4 to Contract #20210081 for Design Services for the Southport 24-inch Force Main to Glades Booster Pump Station.
Attachments: 1. 20210081-06 Amendment #4 signed by KH, 2. 20210081-05-A3, 3. 20210081-05-A2, 4. 20210081-05-A1, 5. 20210081-05
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendment #4 to Contract #20210081 for Design Services for the Southport 24-inch Force Main to Glades Booster Pump Station.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Kimley-Horn and Associates, Inc. ("Consultant")
3. Purpose: To amend the Contract to extend the duration and include Grant Administration Services for the (continued) intent to complete this project.
4. New/Renewal/Modified: Modified.
5. Duration: This Amendment grants additional time through December 2027.
6. Benefits to Port St. Lucie: The Westport Wastewater Treatment Facility ("WWTF") is permitted to treat up to 6.00 million gallons per day ("MGD"). This Project will alleviate flow which would normally go to the Westport WWTF to the Glades Booster Pump Station instead.
7. Cost to Port St. Lucie (Annual and Potential): Additional $660,983.00 for a revised Contract amount of $2,310,543.00.

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve Amendment #4 to Contract #20210081 for the additional time and Grant Administration and CEI Services on behalf of the Utility Systems Department to manage the construction of the new 24-inch force main.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendment #4 to Contract #20210081.
2. Move that the Council not approve Amendment #4 to Contract #20210081 and provide staff with direction.

Background: The Consultant was authorized on April 11, 2022, to perform design and permitting services for Phases 1, 2 and 3, along with construction phase services for Phase 1. The scope of services for construction phase services for Phases 2 and 3 was defined in the original Co...