Title: Ratify Amendment #1 and Approve Amendment #2 to Contract #20230113 for the Tom Mackie Blvd. Extension Phase 4.
Attachments: 1. Amendment #2 signed., 2. Amendment #1., 3. Original Contract.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Ratify Amendment #1 and Approve Amendment #2 to Contract #20230113 for the Tom Mackie Blvd. Extension Phase 4.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Dickerson Infrastructure, Inc. d/b/a Dickerson Florida, Inc.
3. Purpose: Amend the Contract to provide additional pay items not included in the original Contract.
4. New/Renewal/Modified: Modified.
5. Duration: Additional calendar days are required to install new pay items. The new end date after Amendment #2 is March 8, 2026.
6. Benefits to Port St. Lucie: The construction of the Tom Mackie Boulevard & Marshall Parkway Project will continue the overall development of the Legacy Park at Tradition Center for Commerce.
7. Cost to Port St. Lucie (Annual and Potential): Amendment #1 was for $102,858.80 and Amendment #2 is for $268,059.91 for a new Contract total of $8,903,407.11.

Presentation Information: N/A.

Staff Recommendation: Move that the Council ratify Amendment #1 and approve Amendment #2 to Contract #20230113 for the Tom Mackie Blvd. Extension Project Phase 4 with Dickerson Infrastructure, Inc. d/b/a Dickerson Florida, Inc.

Alternate Recommendations:
1. Move that the Council amend the recommendation and ratify Amendment #1 and approve Amendment #2 to Contract #20230113.
2. Move that the Council not ratify Amendment #1 nor approve Amendment #2 to Contract #20230113 and provide staff with direction.

Background: The City Council identified the development of the Southern Grove Master Plan to meet the goals of a diverse local economy and employment opportunities with the initiative of building out Southern Grove, as a strategic priority. In February 2021, the City Council adopted the Southern Gro...