Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendment #1 to Contract #20210116 for the Construction of the Northport 24" Force Main on Glades Cutoff Road.
body
Submitted By: Shelby Dolan, Procurement Contracts Manager, Procurement Management Division.
Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.
Summary Brief (Agreements/Contracts only)
1. Prepared by: Shelby Dolan, Procurement Management.
2. Parties: City of Port St. Lucie and Accurate Drilling Systems, Inc.
3. Purpose: Add a critical interconnection between a newly installed 24-inch Force Main and the two (2) existing Force Mains (12-inch and 16-inch) to the original scope.
4. New/Renewal/Modified: Modified.
5. Duration: The request includes an addition of 224 calendar days for a revised expiration date of August 1, 2023.
6. Benefits to Port St. Lucie: The proposed interconnected is requested by the Utility Systems Department ("USD") to add both capacity and redundancy to the sewer system by creating multiple pathways for sewer flows to reach the Glades Wastewater Treatment Facility.
7. Cost to Port St. Lucie (Annual and Potential): An additional $95,605 be added to the contract for a new Contract Amount of $3,718,425.
Presentation Information: N/A.
Staff Recommendation: Move that the Council approve Amendment #1 to Contract #20210116 for the Construction of the Northport 24" Force Main on Glades Cutoff Road.
Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendment #1 to Contract #20210116.
2. Move that the Council not approve Amendment #1 to Contract #20210116 and provide staff with direction.
Background: The contractor was awarded the installation of 9,200 LF of 24-inch Force Main along Glades Cutoff Road to provide additional points of connection for future customers and to assist in the improvement of the system hydraulics throughout the City. A beneficial interconnection bet...
Click here for full text