File #: 2022-129    Version: 1 Name:
Type: Consent Status: Passed
File created: 2/1/2022 In control: City Council
On agenda: 2/14/2022 Final action: 2/14/2022
Title: Approve Amendment #1 to Contract #20210053R for the Rehabilitation / Repair of Water Control Structures #A-22, A-24 & One (1) BSL-2 Twin Culverts at the A-2 Pond with Custom Built Marine Construction, Inc.
Attachments: 1. Contractor Executed Amendment #1.
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendment #1 to Contract #20210053R for the Rehabilitation / Repair of Water Control Structures #A-22, A-24 & One (1) BSL-2 Twin Culverts at the A-2 Pond with Custom Built Marine Construction, Inc.
body
Submitted By: Michelle Fentress, Procurement Agent I, Procurement Management Department (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Michelle Fentress, Procurement Agent I, PMD.
2. Parties: City of Port St. Lucie and Custom Built Marine Construction, Inc.
3. Purpose: To provide improvements to existing control structures located within the Watershed A basin of the City of Port St. Lucie.
4. New/Renewal/Modified: Modified.
5. Duration: The initial term began on November 15, 2021 and will terminate on November 25, 2022. An additional 14 days is necessary for the additional work. The new end date will be December 09, 2022.
6. Benefits to Port St. Lucie: To aid in better functionality of existing water control structures.
7. Cost to Port St. Lucie (Annual and Potential): The original estimated expenditure was for $1,532,885. This amendment is to add additional services in the amount of $98,068.58. Therefore, the total estimated expenditure is $1,630,953.58.

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve Amendment #1 to Contract #20210053R for the Rehabilitation / Repair of Water Control Structures #A-22, A-24 & one (1) BSL-2 Twin Culverts at the A-2 Pond with Custom Built Marine Construction, Inc.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendment #1 to Contract #20210053R.
2. Move that the Council not approve Amendment #1 to Contract #20210053R and provide staff with direction.

Background: The A-22, A-24 and BSL structures are a critical component of the stormwater system as they are located a...