Placement: Consent Agenda
Action Requested: Motion / Vote
title
Award Contract #20230041 for the Traffic Calming Construction Project at Various Locations.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).
Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.
Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Pav-Co Contracting, Inc.
3. Purpose: To ensure the overall safety and livability of residential neighborhoods.
4. New/Renewal/Modified: New.
5. Duration: 120 calendar days with no option to renew.
6. Benefits to Port St. Lucie: To enhance safety in residential neighborhoods.
7. Cost to Port St. Lucie (Annual and Potential): One-time expense of $532,596.98.
Presentation Information: N/A.
Staff Recommendation: Move that the Council award Contract #20230041 and enter into a fixed unit price contract for the Traffic Calming Construction Project with Pav-Co Construction, Inc.
Alternate Recommendations:
1. Move that the Council amend the recommendation and award Contract #20230041.
2. Move that the Council not approve Contract #20230041 and provide staff with direction.
Background: The City of Port St. Lucie is committed to ensuring the overall safety and livability of residential neighborhoods. One way to meet this commitment is through a collaboration of City staff and property owners to manage traffic in neighborhoods and address documented traffic concerns. The City of Port St. Lucie Traffic Calming Policy provides a process to evaluate and implement appropriate traffic calming measures.
Ballots were mailed to residents in and adjacent to the proposed project limits in order to survey support for the traffic calming measures. Of the returned ballots, support exceeded the pre-determined 75% threshold required to move forward with construction.
An E-Bid was issued on March 23, 2023 to 1, 654 potential suppliers. There...