title
Resolution 23-R34, A Resolution Approving the Preliminary and Final Plat with Construction Plans for Crosstown Parkway Plat 2-A (P22-020)
body
Submitted By: Daniel Robinson, Planner III/Code Compliance Liaison
Strategic Plan Link: The City's Mission to plan for smart and balanced growth.
Executive Summary (General Business): The proposed subdivision plat will create the public right-of- way tract for Crosstown Parkway from the existing termination of Crosstown Parkway, west approximately 7,982 feet.
Presentation Information: Staff may provide a presentation.
Staff Recommendation: Move that the Council approve the resolution as recommended by the Site Plan Review Committee.
Alternate Recommendations:
1. Move that the Council amend the recommendation and approve the resolution.
2. Move that the Council Not approve the resolution and provide direction.
Background: The Site Plan Review Committee recommended approval of the preliminary and final plat and construction plans at their meeting of March 23, 2022.
Issues/Analysis: N/A
Financial Information: N/A
Special Consideration: N/A
Location of Project: South of Verano development and north of Tradition development, western extension of Crosstown parkway west of Village Parkway.
Attachments:
1. Resolution
2. Subdivision Plat
3. Construction Plans - 2A Phase 1
4. Construction Plans - 2A Phase 2
5. Landscape Plan - Section 2-A Only
6. Staff Report
7. Application
8. Public Works Memo
9. Legal bond review memo
10. Staff Presentation
NOTE: All of the listed items in the "Attachment" section above are in the custody of the City Clerk. Any item(s) not provided in City Council packets are available upon request from the City Clerk.
Internal Reference Number: 9139
Legal Sufficiency Review:
Reviewed by Elizabeth L. Hertz, Senior Deputy City Attorney. Approved as to Legal form and sufficiency by James D. Stokes, City Attorney.