Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendment #5 to Contract #20210103 for the Design Services for the Hegener Drive Extension Phase 3 Project.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).
Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.
Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and CAPTEC Engineering, Inc.
3. Purpose: Provide additional services to complete construction plans to 100%.
4. New/Renewal/Modified: Modified.
5. Duration: Add an additional 120 calendar days for a new end date of 9/26/2024.
6. Benefits to Port St. Lucie: Proceeding with 100% construction plans will allow the project to be completed within the time parameters of the state appropriations.
7. Cost to Port St. Lucie (Annual and Potential): An additional $123,890.00 for a new Contract amount of $759,347.00.
Presentation Information: N/A.
Staff Recommendation: Move that the Council approve Amendment #5 to Contract #20210103 for the Design Services.
Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendment #5 to Contract #20210103.
2. Move that the Council not approve Amendment #5 to Contract #20210103 and provide staff with direction.
Background: The project is comprised of three (3) road segments inclusive of potable water distribution, wastewater collection and storm water improvements that can be constructed either concurrently or as stand-alone projects. The project is located on the City of Port St. Lucie Government Finance Corporation (GFC) lands. The description of the three (3) road segments are as follows:
* E/W Road #2 - Finalizing the plans from 60% plans to 100% will be completed by the developer.
* Tom Mackie Blvd. - Extend Tom Mackie Blvd. from approximately 150 feet south of the future intersection of Tom Mackie Blvd. and E/W Road #2 south appr...