File #: 2024-269    Version: 1 Name:
Type: Consent Status: Passed
File created: 3/7/2024 In control: City Council
On agenda: 3/25/2024 Final action: 3/25/2024
Title: Award Contract #20240047 for the Replacement of the Emergency Generator at Building B.
Attachments: 1. 20240047-174 Notice of Intent to Award- NOIA (Legistar Posting), 2. 20240047-08 E-Bid Tabulation Report, 3. 20240047-05 GLF Construction 3, 4. Recommended Proposal, 5. E-Bid Document, 6. Construction Plans
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Award Contract #20240047 for the Replacement of the Emergency Generator at Building B.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and GLF Construction Corporation.
3. Purpose: Replace the small generator at Building B to a larger generator to be able to provide power to the entire building during any outages.
4. New/Renewal/Modified: New.
5. Duration: One hundred eighty-eight (188) calendar days to provide a completion date of 9/30/2024 with no option to renew.
6. Benefits to Port St. Lucie: To ensure that back-up power is provided to Building B during a power outage.
7. Cost to Port St. Lucie (Annual and Potential): The one-time expenditure is $948,900.00.

Presentation Information: N/A.

Staff Recommendation: Move that the Council award Contract #20240047 and enter into a contract with GLF Construction Corporation for the replacement of the emergency generator at Building B.

Alternate Recommendations:
1. Move that the Council reject the recommended bid.
2. Move that the Council reject all bids and provide staff with direction.

Background: The existing generator at Building B needs to be replaced with a larger generator that will be able to run the entire building in the event of a power loss.

An E-Bid was issued on February 2, 2024, to 2,013 potential contractors. There were twenty-one (21) plan holders with two (2) responsive proposals and one (1) non-responsive proposal being received on March 5, 2024.

Issues/Analysis: Staff has reviewed the proposals and finds the GLF Construction Corporation provides the lowest responsive responsible bid. The project is partially funded by a State of Florida Division of Emergency Management Hazard Mitigation Gra...

Click here for full text