City of Port St. Lucie header
File #: 2021-735    Version: 1 Name:
Type: Consent Status: Passed
File created: 8/30/2021 In control: City Council
On agenda: 9/13/2021 Final action: 9/13/2021
Title: Award Contract #20210019 for Electrical Connection of Retrofitted City Grinder Pump Systems with Aapex Electric, Inc.
Attachments: 1. 1. Bid Tabulation Report, 2. 2. Contract, 3. 3. Recommended Proposal, 4. 4. Bid Documents
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Award Contract #20210019 for Electrical Connection of Retrofitted City Grinder Pump Systems with Aapex Electric, Inc.
body
Submitted By: Shelby Dolan, Procurement Agent II, Procurement Management Department.

Strategic Plan Link: The City's Mission to provide exceptional municipal services.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Shelby Dolan, Procurement Management Department.
2. Parties: City of Port St. Lucie and Aapex Electric, Inc.
3. Purpose: To provide electrical connection of retrofitted City grinder pump systems.
4. New/Renewal/Modified: New.
5. Duration: Three years with the option for one additional three-year renewal.
6. Benefits to Port St. Lucie: To provide the electrical connection for grinder control panels to City residents.
7. Cost to Port St. Lucie (Annual and Potential): Per unit price of $995 with an estimated annual expenditure of $477,600. All future expenditures will be appropriated in the proposed budgets for each fiscal year.

Presentation Information: N/A.

Staff Recommendation: Move that the Council award Contract #20210019 and enter into a unit price contract with Aapex Electric, Inc. for the Electrical Connection of Retrofitted City Grinder Pump System.

Alternate Recommendations:
1. Move that the Council amend the recommendation and award Contract #20210019.
2. Move that the Council not approve Contract #20210019 and provide staff with direction.

Background: The Utility System Department plans to complete approximately 500 septic system to City grinder Sewer Conversions per fiscal year. As part of the sewer installation process, an electrical contractor will be responsible to run the dedicated electrical line from the home's main control panel to the designated location for the City grinder control panel. An electrical disconnect box and grinder control panel will be mounted by the electrical contractor.

An E-Bid was issued on...