File #: 2024-284    Version: 1 Name:
Type: Consent Status: Passed
File created: 3/12/2024 In control: City Council
On agenda: 3/25/2024 Final action: 3/25/2024
Title: Approve Amendment #1 to Contract #20230077 for the Anthony F. Sansone Sr. Blvd. Phase 3 Extension.
Attachments: 1. 20230077-06 Amendment #1 signed by JWC, 2. 20230077-05
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendment #1 to Contract #20230077 for the Anthony F. Sansone Sr. Blvd. Phase 3 Extension.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and JW Cheatham, LLC.
3. Purpose: To amend the contract due to the realignment of the road which is needed to facilitate the sale of the Costco Warehouse Distribution (Project Everest) Center.
4. New/Renewal/Modified: Modified.
5. Duration: No additional time is needed.
6. Benefits to Port St. Lucie: The construction of the Anthony F. Sansone Sr. Blvd. will continue the overall development of the Legacy Park at Tradition Center for Commerce.
7. Cost to Port St. Lucie (Annual and Potential): An additional $649,544.06 is needed for the realignment of the roadway from the original plans. The new total for the project is $10,957,095.23.

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve Amendment #1 to Contract #20230077 for the construction of the Anthony F Sansone Sr. Blvd. with JW Cheatham, LLC.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendment #1 to Contract #20230077.
2. Move that the Council not approve Amendment #1 to Contract #20230077 and provide staff with direction.

Background: The City Council identified the development of the Southern Grove Master Plan to meet the goals of a diverse local economy and employment opportunities with the initiative of building out Southern Grove, as a strategic priority. In February 2021, the City Council adopted the Southern Grove Master Plan, as prepared by the Treasure Coast Regional Planning Council, which included findings and recommendations pertaining to infrastructure development needs. ...