File #: 2025-873    Version: 1 Name:
Type: Consent Status: Consent
File created: 9/9/2025 In control: City Council
On agenda: 9/22/2025 Final action:
Title: Ratify Amendments #10 through #13 and Approve Amendment #14 to Contract #20190112 for the Design Services for Floresta Drive Improvements Phases 2 & 3.
Attachments: 1. 20190112-06_Amendment_#14_approved_ABL_Consor Mod_exec, 2. 20190112-05-A13, 3. 20190112-05-A12, 4. 20190112-05-A11, 5. 20190112-05-A10, 6. 20190112-05-A9, 7. 20190112-05-A8, 8. 20190112-05-A7, 9. 20190112-05-A6, 10. 20190112-05-A5, 11. 20190112-05-A4, 12. 20190112-05-A3, 13. 20190112-05-A2, 14. 20190112-05-A1, 15. 20190112-05
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Ratify Amendments #10 through #13 and Approve Amendment #14 to Contract #20190112 for the Design Services for Floresta Drive Improvements Phases 2 & 3.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and CONSOR North America, Inc. fka CONSOR Engineers, LLC fka American Consulting Engineers of Florida, LLC. ("CONSOR").
3. Purpose: Increase funds to allow for additional design services on the D-11 Canal Stabilization Project.
4. New/Renewal/Modified: Modified.
5. Duration: Current End Date is November 19, 2027.
6. Benefits to Port St. Lucie: Additional design will provide for increased stormwater flow and flexibility in construction.
7. Cost to Port St. Lucie (Annual and Potential): Amendment #10 - $13,400.00, Amendment #11 - $62,800.00, Amendment #12 - $14,100.00, Amendment #13 - $0.00*, and Amendment #14 - $49,901.00 for a new Contract total amount of $2,796,015.00.
*There is a cost listed in Amendment #13, however, that was added to correct an accounting error in a previous amendment, not add new funds.

Presentation Information: N/A.

Staff Recommendation: Move that the Council ratify Amendments #10 through #13 and approve Amendment #14 for the Design & Permitting for Floresta Drive Phases 2 & 3 with CONSOR.

Alternate Recommendations:
1. Move that the Council amend the recommendation and ratify Amendments #10 through #13 and approve Amendment #14 to Contract #20190112.
2. Move that the Council not ratify Amendments #10 through #13 nor approve Amendment #14 and provide staff with direction.

Background: Amendment #14 -The design of the D-1 Canal Stabilization Project was awarded to American Consulting Engineers of Florida, LLC for a period between January 7, 2...

Click here for full text