Placement: Consent Agenda
Action Requested: Motion / Vote
title
Ratify Amendments #10 through #13 and Approve Amendment #14 to Contract #20190112 for the Design Services for Floresta Drive Improvements Phases 2 & 3.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).
Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.
Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and CONSOR North America, Inc. fka CONSOR Engineers, LLC fka American Consulting Engineers of Florida, LLC. ("CONSOR").
3. Purpose: Increase funds to allow for additional design services on the D-11 Canal Stabilization Project.
4. New/Renewal/Modified: Modified.
5. Duration: Current End Date is November 19, 2027.
6. Benefits to Port St. Lucie: Additional design will provide for increased stormwater flow and flexibility in construction.
7. Cost to Port St. Lucie (Annual and Potential): Amendment #10 - $13,400.00, Amendment #11 - $62,800.00, Amendment #12 - $14,100.00, Amendment #13 - $0.00*, and Amendment #14 - $49,901.00 for a new Contract total amount of $2,796,015.00.
*There is a cost listed in Amendment #13, however, that was added to correct an accounting error in a previous amendment, not add new funds.
Presentation Information: N/A.
Staff Recommendation: Move that the Council ratify Amendments #10 through #13 and approve Amendment #14 for the Design & Permitting for Floresta Drive Phases 2 & 3 with CONSOR.
Alternate Recommendations:
1. Move that the Council amend the recommendation and ratify Amendments #10 through #13 and approve Amendment #14 to Contract #20190112.
2. Move that the Council not ratify Amendments #10 through #13 nor approve Amendment #14 and provide staff with direction.
Background: Amendment #14 -The design of the D-1 Canal Stabilization Project was awarded to American Consulting Engineers of Florida, LLC for a period between January 7, 2...
Click here for full text