City of Port St. Lucie header
File #: 2023-579    Version: 1 Name:
Type: Consent Status: Passed
File created: 6/22/2023 In control: City Council
On agenda: 7/10/2023 Final action: 7/10/2023
Title: Approve Amendment #1 to Contract #20220044 with Wharton-Smith, Inc. the Westport Wastewater Treatment Facility Nutrient Reduction Improvement Project.
Attachments: 1. Amendment 1 7.2.23-signed, 2. Exhibit A to Amendment 1 Contract 20220044, 3. Exhibit B to Amendment 1 GMP-1 Early Package #1
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendment #1 to Contract #20220044 with Wharton-Smith, Inc. the Westport Wastewater Treatment Facility Nutrient Reduction Improvement Project.
body
Submitted By: Kevin R. Matyjaszek, Utility Systems Director

Strategic Plan Link: The City's Goal of a high-performing city government organization.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Procurement Management Department ("PMD") and Utility Systems Department ("USD").
2. Parties: City of Port St. Lucie and Wharton-Smith, Inc. ("Contractor")
3. Purpose: To amend Contract #20220044 to proceed with the next step in the Westport Nutrient Reduction Improvement Project ("Project") establishing an early estimated Guaranteed Maximum Pricing ("GMP") for the Westport Wastewater Treatment Facility Nutrient Reduction Improvement Project ("Project").
4. New/Renewal/Modified: Modified.
5. Duration: The term for pre-construction services was 180 days. The Contractor is requesting an additional 60 days as part of this Amendment to proceed with purchasing the items which require a long lead time for the Project.
6. Benefits to Port St. Lucie: To provide high quality treatment to reduce nutrients discharged to the St. Lucie River in compliance with new State of Florida Department of Environmental Protection ("FDEP") limits for nitrogen and phosphorous. By reducing the amount of nutrients discharged, it will reduce the growth of algae, improve the water quality, and reduce health effects impacting the St. Lucie River.
7. Cost to Port St. Lucie (Annual and Potential): The estimated cost of pre-construction services was $210,305.00. The Contractor estimates the early GMP in the amount of $6,721,703.00.

Presentation Information: N/A

Staff Recommendation: Move that the Council approve Amendment #1 to Contract #20220044 establishing an early estimated Guaranteed Maximum Price and authorizing the Contractor to proceed with construction and r...