Torino Regional Park Phase 1 Design Updates (Follow-Up Presentation)
body
Submitted By: Zakariya M. Sherman, Executive Project Manager, Parks and Recreation
Strategic Plan Link: The City's Goal to Enjoy Culture, Nature and Recreation.
Executive Summary (General Business): Staff will present updated design details for Torino Regional Park Phase 1, including the current site plan and enhanced visuals of the proposed playground and splash pad amenities.
Presentation Information: Jonathan Haigh, PLA, ASLA, from Kimley-Horn will provide a follow-up presentation on the Torino Regional Park Phase I design. The presentation will include a review of the site plan and more detailed visuals of the proposed playground and splash pad amenities. City staff will also be in attendance to address any questions.
Staff Recommendation: Request that the Council hear the presentation and provide any comments or feedback.
Background: On June 24, 2024, Council approved the Torino Regional Park Conceptual Master Plan (Kimley-Horn) and the Phase 1 Funding and Phasing Recommendation. Phase 1 focuses on Parcel A, a 75-acre site with 62.4 acres of uplands and a 12.5-acre lake.
An amended design contract with Kimley-Horn was approved on October 28, 2024, expanding their continuing services contract to include the Torino design. Kimley-Horn is overseeing all aspects of Phase 1 design, including surveys, geotechnical assessments, environmental services, design phases through final plans and permitting, and specialized design services such as splash pad and skate park design, structural and architectural engineering, and security system design.
The Construction Manager at Risk (CMAR) contract with Burkhardt Construction, Inc. was approved on November 12, 2024, fully encumbering ARPA funds upon execution.
A kickoff meeting was held on November 13, 2024, with Parks and Recreation staff, Kimley-Horn, and Burkhardt. A tentative...