File #: 2021-795    Version: 1 Name:
Type: Consent Status: Passed
File created: 9/16/2021 In control: City Council
On agenda: 9/27/2021 Final action: 9/27/2021
Title: Approve a Waiver of Bid for Purchase of Materials for Naranja Area Sewer Improvements
Attachments: 1. Naranja Area Sewer Improvements Location Map, 2. Ferguson Phase_Naranja LPFM IMP PH I_Price, 3. Ferguson Phase_Naranja LFFM IMP PH II_Price, 4. PSLUSD Letter to FDEP 1.26.21, 5. Core and Main_ Naraja LPFM IMP PH I_Price, 6. Core and Main_Naraja LPFM IMP PH II_Price
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve a Waiver of Bid for Purchase of Materials for Naranja Area Sewer Improvements
body
Submitted By: Brad Macek, Director, Utility Systems Department

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Utility Systems Department (USD).
2. Parties: City of Port St. Lucie and Ferguson Waterworks Inc, a Florida profit corporation.
3. Purpose: The USD is seeking to waive the bidding for acquisition of materials for the Naranja Area Sewer improvements to acquire materials from Ferguson Waterworks, Inc. Felix Associates of Florida, Inc. has agreed to provide the work once materials are received pursuant to Contract #20200043.
4. New/Renewal/Modified: New
5. Duration: As needed
6. Benefits to Port St. Lucie: Repairs to City's wastewater system.
7. Cost to Port St. Lucie (Annual and Potential): Estimated cost of $74,768.60 for materials for Phase I and $24,040.12 for Phase II, for a total estimated cost of $98,808.72.

Presentation Information: N/A

Staff Recommendation: Move that the Council waive bidding, per Chapter 35.04(c) of the City's code of ordinances, for good cause shown and approve the immediate purchase of materials from Ferguson Waterworks needed for immediate repairs to the Naranja and RiverPark area wastewater system.

Alternate Recommendations:
1. Move that the Council amend the recommendation and complete the motion in the affirmative.
2. Move that the Council not approve and provide staff with direction.

Background: The COVID pandemic has impacted the USD in many ways - one of the largest impacts are to staff and materials shortages resulting in current City contracts and contractors unable to honor pricing. Blue Goose Construction, LLC and Felix Associates of Florida, Inc., both under contract with the City (pursuant to E-bid #20200043), were unable to honor their material pricing du...

Click here for full text