Award Contract #20230060 for the Construction of the Deep Injection Well #2 at the Prineville Water Treatment Facility.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).
Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.
Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Youngquist Brothers, LLC ("Contractor").
3. Purpose: To provide a redundant well for the disposal of reverse osmosis concentrate.
4. New/Renewal/Modified: New.
5. Duration: 900 calendar days with no option to renew.
6. Benefits to Port St. Lucie: The proposed deep injection well will provide redundancy of the existing well and maintain the ability to produce 11.15 million gallons a day of water through our reverse osmosis treatment process.
7. Cost to Port St. Lucie (Annual and Potential): One-time expense of $13,986,482.00 plus a city owned contingency of $500,000.00 for a total budget of $14,486,482.00.
Presentation Information: N/A.
Staff Recommendation: Move that the Council award Contract #20230060 and enter into a unit price contract with Youngquist Brothers, LLC for the Construction of the Deep Injection Well #2 at the Prineville Water Treatment Facility.
Alternate Recommendations:
1. Move that the Council amend the recommendation and award Contract #20230060.
2. Move that the Council not award Contract #20230060 and provide staff with direction.
Background: The City of Port St. Lucie owns and operates the Prineville Water Treatment Facility deep injection well system for disposal of concentrate from the reverse osmosis (RO) process. The deep injection well system currently consists of one Class I deep injection well (IW-1) and associated dual-zone monitor well (MW-1), a surge control system, yard piping and instrumentation. The Prineville IW-1 has been operational since 2011. The...
Click here for full text