Placement: Consent Agenda
Action Requested: Motion / Vote
title
Award Contract #20220078 for the Winterlakes Park Phase 2 Improvement Project.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Department (PMD).
Strategic Plan Link: The City's Goal of a high-performing city government organization.
Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Paul Jacquin & Sons, Inc.
3. Purpose: Provide construction services for the Winterlakes Park Phase 2 project.
4. New/Renewal/Modified: New.
5. Duration: 270 calendar days with no option for renewal.
6. Benefits to Port St. Lucie: Winterlakes Park Phase 2 project has been planned and designed to aid the City with addressing its Strategic Goal #6 Culture, Nature and Fun Activities. Winterlakes Park Phase 2 construction will provide residents with additional requested amenities at the existing park site.
7. Cost to Port St. Lucie (Annual and Potential): One-time expense of $1,442,629.00.
Presentation Information: N/A.
Staff Recommendation: Move that the Council award Contract #20220078 and enter a unit price contract with Paul Jacquin & Sons, Inc., for the Winterlakes Park Phase 2 Improvement Project in the amount of $1,442,629.00.
Alternate Recommendations:
1. Move that the Council amend the recommendation and award Contract #20220078.
2. Move that the Council not approve Contract #20220078 and provide staff with direction.
Background: From 2007 to 2012, the City leased the property to the St. Lucie County School District for the purpose of constructing a temporary school site. The School District cleared and graded the property, designed and permitted the storm water collection system, installed underground drainage, constructed a wet retention pond, constructed asphalt parking lots and driveways, constructed interior sidewalks, and an open-sided "airnasium," brought water/sewer/electric services to the site and built a pl...
Click here for full text