Title: Approval to Participate in the City of Kissimmee's Contract IFB 2022-002 for Alternative Paving Methods.
Attachments: 1. City of Port St. Lucie Piggyback Agreement, 2. City of Kissimmee's IFB 2022-002, 3. City of Kissimmee's Contract 2022-002, 4. City of Kissimmee Bid Tabulation, 5. Proof of Advertisement
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approval to Participate in the City of Kissimmee's Contract IFB 2022-002 for Alternative Paving Methods.
body
Submitted By: Keith Stewart, Procurement Manager.

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Keith Stewart, Procurement Manager, PMD.
2. Parties: City of Port St. Lucie, Asphalt Paving System, Inc. and all awarded Contractors.
3. Purpose: To rehabilitate failing roadways.
4. New/Renewal/Modified: New.
5. Duration: The initial term began on June 21, 2022 through September 20, 2025, with the option to renew for two (2) additional 1-year periods ending September 20, 2027.
6. Benefits to Port St. Lucie: The ability to maintain safe roadways for the citizens and visitors of Port St Lucie.
7. Cost to Port St. Lucie (Annual and Potential): Current identified project: SW Oriole Lane for $165,000.00. Future expenditures will be appropriated in the approved budgets for each fiscal year through September 20, 2027.

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve participating in the City of Kissimmee's Contract IFB 2022-002, per Chapter 35.08 (9)(b) with Asphalt Paving System, Inc. and all awarded Contractors for Alternative Paving Methods.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve participating in the City of Kissimmee's Contract IFB 2022-002 for Alternative Paving Methods.
2. Move that the Council not approve participating in the City of Kissimmee's Contract IFB 2022-002 for Alternative Paving Methods and provide staff direction.

Background: This contract is being utilized to accomplish roadway rehabilitation projects that are identified through the City's pavement condition surveys and further verified through field observations. When a roadway's pavement condition index appears to decrease at an accelerate...