Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approval to Participate in the GSA Contract #47QTCA25D002W with Woolpert, Inc., City Master Professional Service Agreement #20260073 for Risk Framework Development.
body
Submitted By: Autumn Bryan, Procurement Contracting Officer I, Office of Management and Budget, Procurement Management Division (PMD).
Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.
Summary Brief (Agreements/Contracts only)
1. Prepared by: Autumn Bryan, Procurement Contracting Officer I, PMD.
2. Parties: City of Port St. Lucie and Woolpert, Inc.
3. Purpose: To provide the Utility Systems Department (USD) with an as needed professional services agreement for the maintenance and support of its GIS and Cityworks asset management systems and programs.
4. New/Renewal/Modified: New.
5. Duration: The GSA Contract Term is for an initial five (5)-year period ending December 9, 2029, with three (3) additional five (5)-year renewal options.
6. Benefits to Port St. Lucie: This will benefit the USD by developing a first-generation Risk Framework for water distribution, wastewater collection, and conveyance asset classes. The resulting risk framework can then be applied to the USD's individual assets to identify high-risk assets, inform asset management plans, and aid in the identification and development of rehabilitation and replacement projects.
7. Cost to Port St. Lucie (Annual and Potential): Initial term cost is $160,000.00 for FY26. Future expenditures will be appropriated in each fiscal year budget.
Presentation Information: N/A.
Staff Recommendation: Move that the Council approve, pursuant to City Code of Ordinances, Section 35.08(a)(9)(a) (cooperative exception to formal solicitation), participation in the GSA Contract #47QTCA25D002W under Master Professional Services Agreement Contract #20260073 with Woolpert, Inc.
Alternate Recommendations:
1. Move that the Council amend the recomm...