Title: Approve Amendment #6 to Contract #20200054 for the Construction of the Floresta Drive Improvement Project - Phase 1.
Attachments: 1. Location Map for Phase I, 2. 20200054-05-A6 signed, 3. 20200054-05-A5, 4. 20200054-05-A4, 5. 20200054-05-A3, 6. 20200054-05-A2, 7. 20200054-05-A1, 8. 20200054-05
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendment #6 to Contract #20200054 for the Construction of the Floresta Drive Improvement Project - Phase 1.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Department (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Felix Associates of Florida, Inc.
3. Purpose: This is the final Amendment for Floresta Phase 1 that represents additional work and new work requested to complete the project along with final adjustments to bid quantities.
4. New/Renewal/Modified: Modified.
5. Duration: Construction for Floresta Drive Phase 1 started in September 2020. Additional days were added to the contract due to weather, holidays, additional work requests, new work requests and material delays outside of the contractor's control. On Amendment #6, a total of 331 days were added to complete the project for the final completion date of January 31, 2023.
6. Benefits to Port St. Lucie: To facilitate the completion of the project without impeding ongoing construction activities.
7. Cost to Port St. Lucie (Annual and Potential): An additional $363,877.27 to be added to the contract resulting in the final Contract amount of $12,387,450.30.

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve Amendment #6 to Contract #20200054 for the Floresta Drive Improvement Project Phase 1 with Felix Associates of Florida, Inc.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendment #6 to Contract #20200054.
2. Move that the Council not approve Amendment #6 to Contract #20200054 and provide staff with direction.

Background: The Floresta Drive Improvement Project has long been a priority project for the City Council and the City of Port St. Lucie. The project was or...