File #: 2025-1053    Version: 1 Name:
Type: Consent Status: Consent
File created: 10/24/2025 In control: City Council
On agenda: 11/10/2025 Final action:
Title: Ratify Amendment #1 and Approve Amendment #2 to Contract #20240082 for the Floresta Drive Improvements Project Phase 3.
Attachments: 1. Amendment_#2 signed., 2. Amendment #1., 3. Original Contract.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Ratify Amendment #1 and Approve Amendment #2 to Contract #20240082 for the Floresta Drive Improvements Project Phase 3.
body
Submitted By: Robyn older, CPPB, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Felix Civil Construction, LLC.
3. Purpose: To amend the construction services contract for the Floresta Drive Improvements Project Phase 3.
4. New/Renewal/Modified: Modified.
5. Duration: An additional 60 calendar days are needed for a new end date of February 14, 2028.
6. Benefits to Port St. Lucie: The project will complete the construction of Floresta Drive from Crosstown Parkway to Prima Vista Boulevard as a complete street providing bike lanes, sidewalks, traffic calming, streetlights, and landscaping.
7. Cost to Port St. Lucie (Annual and Potential): An additional $808,530.00 is required for this work for a new Contract amount of $51,702,865.18.

Presentation Information: N/A.

Staff Recommendation: Move that the Council ratify Amendment #1 and approve Amendment #2 to Contract #20240082 for the Construction of Floresta Drive Improvements Project Phase 3 with Felix Civil Construction, LLC.

Alternate Recommendations:
1. Move that the Council amend the recommendation and ratify Amendment #1 and approve Amendment #2 to Contract #20240082.
2. Move that the Council not ratify Amendment #1 nor approve Amendment #2 and provide staff with direction.

Background: Improvements to the Floresta Drive corridor were a priority for the City Council and at the 2017 Summer Retreat, Council directed staff to model the corridor, from a traffic standpoint, for both a 2-lane and 4-lane roadway section. The new modeling was performed, and included it the new Crosstown Parkway Extension Project connection to ...

Click here for full text