File #: 2025-954    Version: 1 Name:
Type: Consent Status: Consent
File created: 9/26/2025 In control: City Council
On agenda: 10/13/2025 Final action:
Title: Ratify Amendment #7 and Approve Amendment #8 to Contract #20230117 for CEI & GEO Services for the Port St. Lucie Blvd. North Segment 3 Project.
Attachments: 1. Amendment_#8_signed., 2. Amendment #7., 3. Amendment #6., 4. Amendment #5., 5. Amendment #4., 6. Amendment #3., 7. Amendment #2., 8. Amendment #1., 9. Original Contract.
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Ratify Amendment #7 and Approve Amendment #8 to Contract #20230117 for CEI & GEO Services for the Port St. Lucie Blvd. North Segment 3 Project.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Johnson, Mirmiran & Thompson, Inc. (JMT).
3. Purpose: To provide an increase in funding and time to the CEI & GEO contract to align said contract funding & time with the anticipated total contract time of construction.
4. New/Renewal/Modified: Modified.
5. Duration: New project end date is November 30, 2025.
6. Benefits to Port St. Lucie: The project will provide additional intersection capacity, accessible multi-use pathways, pedestrian lighting, underground drainage and upgraded water and sanitary facilities.
7. Cost to Port St. Lucie (Annual and Potential): Additional $143,990.00 for a new contract amount of $1,683,475.00.

Presentation Information: N/A.

Staff Recommendation: Move that the Council ratify Amendment #7 and approve Amendment #8 to Contract #20230117 for the CEI & GEO Services for the Port St. Lucie Blvd. North Segment 3 Project with Johnson, Mirmiran & Thompson, Inc.

Alternate Recommendations:
1. Move that the Council amend the recommendation and ratify Amendment #7 and approve Amendment #8 to Contract #20230117.
2. Move that the Council not ratify Amendment #7 nor approve Amendment #8 to Contract #20230117 and provide staff with direction.

Background: On September 12, 2023, the City of Port St. Lucie executed a contract with Johnson, Mirmiran & Thompson, Inc. for CEI & GEO Services for the above referenced project. The contract commenced on September 12, 2023, and originally terminated 200 calendar days thereafter on March 30, 2024. The original co...