File #: 2023-449    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/10/2023 In control: City Council
On agenda: 5/22/2023 Final action: 5/22/2023
Title: Resolution 23-R56, A Resolution Approving and Accepting the Preliminary Plat with Construction Plans for Marshall Parkway at Southern Grove, within the City of Port St. Lucie, Florida on the request of Culpepper and Terpening, Inc. (P23-048)
Attachments: 1. Resolution, 2. Marshall Parkway at Southern Grove Preliminary Plat, 3. Construction Plans, 4. Preliminary Landscape Plans, 5. Staff Report, 6. Application, 7. Warranty Deeds, 8. Staff Presentation
Placement: Resolutions
Action Requested: Motion / Vote
title
Resolution 23-R56, A Resolution Approving and Accepting the Preliminary Plat with Construction Plans for Marshall Parkway at Southern Grove, within the City of Port St. Lucie, Florida on the request of Culpepper and Terpening, Inc. (P23-048)
body
Submitted By: Bridget Kean, AICP, Senior Planner

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Executive Summary (General Business): Mattamy Palm Beach, LLC, has applied for preliminary plat approval with construction plans for construction of Marshall Parkway from its current terminus at the roundabout at Del Webb at Tradition to SW Community Boulevard.

Presentation Information: Staff may provide a short presentation.

Staff Recommendation: Move that the Council adopt the resolution approving the preliminary plat with construction plans as recommended by the Site Plan Review Committee and subject to the condition listed in the resolution as recommended by the Public Works Department and further described below:

1. Mattamy Palm Beach, LLC, or it's successors, shall provide corner clips for the road right-of-way at the NE and SE corners of Marshall Pkwy and Community Blvd prior to Final Plat approval. The City will not entertain any request to accept the roadway for ownership and maintenance until this is accomplished.

Alternate Recommendations:
1. Move that the Council amend the recommendation and adopt the resolution approving the preliminary plat with construction plans subject to the condition noted above.
2. Move that the Council not approve and provide staff direction.

Background: The Site Plan Review Committee recommended approval of the preliminary plat with construction plans at the April 12, 2023 Site Plan Review Committee meeting.

Issues/Analysis: Mattamy Palm Beach, LLC, as the developer of the Southern Grove DRI, is responsible for the construction of Marshall Parkway between SW Vill...