Title: Approve Amendment #2 to Contract #20230117 for the Construction Engineering & Inspection (CEI) Services for the Port St. Lucie Blvd. Segment 3 Reconstruction Project.
Attachments: 1. 20230117-06 Amendment signed by JMT, 2. 20230117-05-A1, 3. 20230117-05
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendment #2 to Contract #20230117 for the Construction Engineering & Inspection (CEI) Services for the Port St. Lucie Blvd. Segment 3 Reconstruction Project.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Johnson, Mirmiran & Thompson, Inc. (JMT)
3. Purpose: To increase the funding and time to the CEI and GEO contract to align said contract with the anticipated total contract time for the construction.
4. New/Renewal/Modified: Modified.
5. Duration: An additional 100 calendar days for a proposed new end date of December 9, 2024.
6. Benefits to Port St. Lucie: The Port St. Lucie Blvd. Segment 3 Project will provide additional intersection capacity, assessable multi-use pathways, pedestrian lighting, underground drainage and upgraded water and sewer facilities.
7. Cost to Port St. Lucie (Annual and Potential): An additional $442,564.50 for a new Contract amount of $1,102,220.50

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve Amendment #2 to Contract #20230117 for the CEI Services for the Port St. Lucie Blvd. Segment 3 Reconstruction Project with Johnson, Mirmiran & Thompson, Inc.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendment #2 to Contract #20230117.
2. Move that the Council not approve Amendment #2 to Contract #20230117 and provide staff with direction.

Background: On September 12, 2023, the City executed a contract with Johnson, Mirmiran & Thompson, Inc. for the Construction Engineering & Inspection (CEI) services for the Port St. Lucie Blvd. Segment 3 Reconstruction Project. This contract commenced on September 12, 2023, and originally terminated 200 calen...

Click here for full text