File #: 2025-047    Version: 1 Name:
Type: Consent Status: Consent
File created: 12/30/2024 In control: City Council
On agenda: 1/13/2025 Final action:
Title: Approve Change Order #3 to Contract #20220096 with H. J. High Construction for the Design-Build of the Police Training Facility Project.
Attachments: 1. Change Order #3 Signed., 2. Change Order #2., 3. Change Order #1., 4. Original Contract.
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Change Order #3 to Contract #20220096 with H. J. High Construction for the Design-Build of the Police Training Facility Project.
body
Submitted By: Nathaniel Rubel, Procurement Assistant Director, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of safe, clean, and beautiful.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Nathaniel Rubel, Procurement Assistant Director, PMD.
2. Parties: City of Port St. Lucie and H. J. High Construction.
3. Purpose: To amend Contract #20220096 for additional costs due to project revisions required by the South Florida Water Management District (SFWMD).
4. New/Renewal/Modified: Modified.
5. Duration: Contract duration is increased by 77 days for a new Substantial Completion date of 03/23/2026.
6. Benefits to Port St. Lucie: Provides a dedicated facility that can be tailored to meet specific departmental needs, ensuring that training aligns with the challenges officers may face in the community.
7. Cost to Port St. Lucie (Annual and Potential): An additional $308,947.08 for a new Contract total of $28,358,653.08.

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve Change Order #3 to Contract #20220096 with H. J. High Construction Company for the construction of the Police Training Facility.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Change Order #3.
2. Move that the Council not approve Change Order #3 and provide staff with direction.

Background: On August 21, 2023, Council awarded a Contract to H. J. High Construction Company for the Design-Build of the Police Training Facility. The original Contract was for the design, bidding, and permitting phase services in the amount of $2,102,945.00. The original plan for the building design was a two-story building with an empty second floor shell space. Change Order #1 was approved by Coun...