Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Task Order #20260337 for Peacock Building Renovations - Fire Sprinkler, Plumbing, and Electrical - CMAR Phase 3.
body
Submitted By: Alaina Knofla, Procurement Manager, Procurement Management Division, (PMD).
Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.
Summary Brief (Agreements/Contracts only)
1. Prepared by: Alaina Knofla, Procurement Manager, (PMD).
2. Parties: City of Port St. Lucie and The Morganti Group, Inc.
3. Purpose: This task order incorporates additional work associated with Contractor's final GMPs for the Peacock Project, Phase 3: Fire Sprinklers, Plumbing, Electrical.
4. New/Renewal/Modified: New.
5. Duration: This task order shall be completed within one hundred fifty-one (151) calendar days from the day it is fully executed.
6. Benefits to Port St. Lucie: Efficient and operable facility and infrastructure.
7. Cost to Port St. Lucie (Annual and Potential): One-time expense of $2,748,553.00.
Presentation Information: N/A.
Staff Recommendation: Move that the Council approve Task Order #20260336 with The Morganti Group, Inc., for the renovation of the Peacock Building-Phase 3: Fire Sprinkler, Plumbing, and Electrical.
Alternate Recommendations:
1. Move that the Council amend the recommendation and approve the Task Order #20260337 with The Morganti Group, Inc.
2. Move that the Council not approve Task Order #20260336 and provide staff with direction.
Background: On July 30, 2025, the City acquired the building located at 300 NW Peacock Blvd., with the intent of consolidating the land development functions from five departments into a single, centralized location. During due diligence, it was determined that the facility was not functional in its current condition and would require full renovation to meet operational needs. This project reflects the City's commitment to recommissioning and fully outfitting the building to p...