Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendments #1, #2 & #3 to Contract #20220032 for the Construction of The Port District - Park & Playground Infrastructure Improvement Project with Ferreira Construction Co., Inc.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Department (PMD).
Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.
Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Ferreira Construction Co., Inc.
3. Purpose: To construct all necessary infrastructure for the new "WOW" playground and park at Westmoreland.
4. New/Renewal/Modified: Modified.
5. Duration: An additional 100 calendar days for a new end date of August 6, 2023.
6. Benefits to Port St. Lucie: To provide a unique destination for the residents of Port St. Lucie.
7. Cost to Port St. Lucie (Annual and Potential): An additional net total amount of $31,376.03 (Amendment #1 - $2,500.00, Amendment #2 - $19,044.60 & Amendment #3 - $9,831.43). The new Contract amount is $9,940,398.97.
Presentation Information: N/A.
Staff Recommendation: Move that the Council approve Amendments #1, #2 & #3 to Contract #20220032 for The Port District - Park & Playground Infrastructure & Improvement Project with Ferreira Construction Co., Inc.
Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendments #1, #2 & #3 with Ferreira Construction Co., Inc.
2. Move that the Council not approve Amendments #1, #2 & #3 to Contract #20220032 and provide staff with direction.
Background: The Westmoreland Middle Tract has long been identified as a unique gathering place along the North Fork of the St. Lucie River. Recent efforts to improve the visitor experience include the installation of a boardwalk along the river, in addition to continued improvements to the City's Botanical Gardens.
The project was bid in February of 202...
Click here for full text