Title: Approve Amendments #4 & #5 to Contract #20220032 for the Construction of The Port District - Park & Playground Infrastructure Improvement Project.
Attachments: 1. 20220032 Attachment C - Project Location Map, 2. 20220032-06 Amendment #5, 3. 20220032-06 Amendment #4, 4. 20220032-05-A3, 5. 20220032-05-A2, 6. 20220032-05-A1, 7. 20220032-05
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Placement: Consent Agenda
Action Requested: Motion / Vote
title
Approve Amendments #4 & #5 to Contract #20220032 for the Construction of The Port District - Park & Playground Infrastructure Improvement Project.
body
Submitted By: Robyn Holder, CPPB, Procurement Management Division (PMD).

Strategic Plan Link: The City's Goal of high-quality infrastructure and facilities.

Summary Brief (Agreements/Contracts only)
1. Prepared by: Robyn Holder, CPPB (PMD).
2. Parties: City of Port St. Lucie and Ferreira Construction Co., Inc.
3. Purpose: To construct all necessary infrastructure for the "WOW" Park on Westmoreland Blvd.
4. New/Renewal/Modified: Modified.
5. Duration: An additional 201 calendar days are required for the additional scope of work. New proposed end date is February 23, 2024.
6. Benefits to Port St. Lucie: To provide a premier destination within the City of Port St. Lucie. This area will bring a diverse array of recreation and leisure opportunities for all to enjoy.
7. Cost to Port St. Lucie (Annual and Potential): An additional $733,274.44 for Amendment #4 and an additional $1,373,636.38 for Amendment #5. The new Contract amount is $12,047,309.79.

Presentation Information: N/A.

Staff Recommendation: Move that the Council approve Amendments #4 & #5 to Contract #20220032 for The Port District - Park & Playground Infrastructure Improvement Project with Ferreira Construction Co., Inc. Both Amendments are requested to be processed at the same time to separate the funding sources.

Alternate Recommendations:
1. Move that the Council amend the recommendation and approve Amendments #4 & #5 to Contract #20220032.
2. Move that the Council not approve the Amendments and provide staff with direction.

Background: The Westmoreland Middle Tract has long been identified as a unique gathering place along the North Fork of the St. Lucie River. Recent efforts to improve the visitor experience include the installation of a boardwalk along the river, in additi...